Palos Verdes Estates, CA
Home MenuAnnual Slurry Seal Project (FY25-26)
Construction Notice
Annual Slurry Seal Project (FY25/26)
City Project No. PW-720-25
Slurry Seal Application Scheduled for August 3–5, 2026
Slurry seal application is scheduled to take place on designated streets in the Lunada Bay area from Monday, August 3 through Wednesday, August 5, 2026.
During application, affected streets will be fully closed to pedestrian and vehicle traffic from 7:00 A.M. to 4:00 P.M., or until the pavement is completely dry.
Please observe all posted “No Parking” signs and traffic-control directions. Work is currently scheduled only for August 3–5.
Project Overview
The City of Palos Verdes Estates awarded a construction contract to Pavement Coatings Co. for the FY25/26 Annual Slurry Seal Project within the Lunada Bay area.
Preparatory work is scheduled to begin on July 13, 2026. Application of the slurry seal treatment is scheduled to begin on August 3, 2026, and the Project is anticipated to be completed by August 28, 2026.
Working hours are 7:00 A.M. to 4:00 P.M., Monday through Friday. The schedule may change due to weather, construction conditions, or other unforeseen circumstances.
Key Project Dates
Project Map and Documents
Review the documents below to determine whether your street is included and the scheduled date of slurry seal application.
Street-by-Street Schedule
View the complete list of streets and scheduled application dates.
View Schedule ListApplication Schedule Map
View the color-coded map showing the scheduled application date for each Project street.
View Project MapConstruction Notice
Download the complete resident construction notice for the FY25/26 Annual Slurry Seal Project.
Download NoticeSample Door-Hanger Notice
View the notice that will be distributed to affected homes before work occurs.
View Door HangerSlurry Seal Application Schedule
The scheduled streets are listed below. Please refer to posted “No Parking” signs and the door-hanger notice delivered to your home for the exact closure date and time applicable to your property.
| Date | Street | From | To |
|---|---|---|---|
| Monday August 3 |
Plaza Francisco | Via Asturias | Via Castilla |
| Via Asturias | Via Castilla | Via Castilla | |
| Via Castilla | Via Barcelona | Cul-de-sac | |
| Via Valdes | Via Olivera | Via Zumaya | |
| Via Romero | Via Carrillo | Via Zumaya | |
| Via Descanso | Via Estudillo | Cul-de-sac | |
| Via Estudillo | Dolores Plaza | Via Olivera | |
| Dolores Plaza | Via Coronel | Via Coronel | |
| Via Landeta | Via Garfias | Via Zurita | |
| Via Landeta | Via Zurita | Via Coronel | |
| Via Martinez | Via Lopez | Via Zurita | |
| Tuesday August 4 |
Via Castilla | Via Barcelona | Via Zumaya |
| Via Davalos | Via Coronel | Cul-de-sac | |
| Zorillos Place | Via Coronel | Cul-de-sac | |
| Plaza Blanca | Via Coronel | Via Coronel | |
| Muros Place | Via Coronel | Cul-de-sac | |
| Via Leon | Via Coronel | Cul-de-sac | |
| Noya Place | Via Coronel | Cul-de-sac | |
| Via Margate | Palos Verdes Drive West | Via Boronada | |
| Via Boronada | Via Margate | Palos Verdes Drive West | |
| Via Curva | Via Coronel | Via Coronel | |
| Via Zurita | Via Fernandez | Via Coronel | |
| Wednesday August 5 |
Via Boronada | Via Margate | Via Coronel |
| Via Estudillo | Espinosa Circle | Rico Place | |
| Rico Place | Via Estudillo | Cul-de-sac | |
| Via Sanchez | Via Olivera | Via Olivera | |
| Plaza Andres | Via Castilla | Via Andres | |
| Via Andres | Via Castilla | Cul-de-sac | |
| Via Galicia | Via Castilla | Cul-de-sac | |
| Via Castilla | Via Coronel | Via Zumaya | |
| Via Lopez | Via Fernandez | Via Zurita |
Scope of Work
The Project includes:
- Slurry seal application, curing, and monitoring.
- Crack sealing to fill pavement cracks before slurry seal placement.
- Localized asphalt patching.
- Removal and replacement of pavement striping and markings.
What Is Slurry Seal?
Slurry seal is a mixture of liquid asphalt and sand that is applied to streets to protect the asphalt and underlying roadway from water damage and ultraviolet rays. It also helps increase skid resistance and extends the life of the existing pavement.
When slurry seal is first applied, it may appear light brown. As the material is exposed to heat and sunlight, it will gradually turn black. The finished surface will have a rougher appearance than a newly overlaid street.
Residents may notice some shedding of small rocks for approximately four to six weeks after application. This is normal and the loose material will be collected during future street-sweeping operations. The slurry seal may take several months to fully cure.
Vehicle movement on recently treated streets may also create temporary tire marks, commonly called power-steering marks. Although these marks may initially affect the appearance of the street, they will fade over time.
Street Closures and No Parking
During slurry seal application, vehicle and pedestrian access within the work area will be temporarily restricted until the new surface has adequately cured.
Because many streets in the City do not have sidewalks, residents who walk, jog, walk dogs, ride bicycles, use strollers, or participate in other outdoor activities may encounter temporary closures and detours.
Most affected streets will be fully closed to through vehicle and pedestrian traffic during application.
Entering a street where slurry seal has recently been applied can damage the new pavement and may cause slurry material to stick to shoes, pet paws, bicycle tires, strollers, and other equipment.
“No Parking” signs showing the exact closure date will be posted near the work area at least 48 hours in advance. A door-hanger notice will also be distributed to affected homes. In most cases, streets will reopen by 4:00 P.M. or after the pavement is fully dry.
How Residents Can Help
Please help ensure the slurry seal can cure properly by following these instructions:
- Avoid the active work area and follow all posted signs and traffic-control directions.
- Use alternate routes until the roadway has reopened to the public.
- Remove vehicles from the street by the time shown on the posted “No Parking” signs.
- Carefully verify the date shown on the signs, as adjacent streets may be scheduled on different days.
- Do not drive, walk, bicycle, or travel across wet slurry seal.
- Do not operate sprinkler systems on the day of application or for 24 hours afterward.
- Prevent irrigation water or other runoff from entering the street, as water can damage the slurry seal material.
Trash Pickup and Street Sweeping
The contractor will coordinate with Athens Services to allow for normal trash pickup operations or to arrange for trash pickup before the affected street is closed.
Street sweeping will be temporarily suspended in affected areas to allow the slurry seal to properly cure. Vehicles will not be cited on scheduled street-sweeping days in areas affected by the slurry seal Project.
Contact Information
The City appreciates the community’s patience and cooperation while these important pavement-preservation improvements are completed.
If you have questions, please contact:
Pavement Coatings Co.
Marc Mumford – Superintendent
Phone: (714) 713-7980
City of Palos Verdes Estates
Chuck Wilson – Public Works Inspector
Phone: (909) 530-8245